The most argued-over numbers in a sortation project are not the ones in the proposal. They are the two in the performance clause: parcels per hour and sort accuracy. A performance guarantee is the mechanism that removes the ambiguity, and liquidated damages are the mechanism that give the guarantee consequences.
For the buyer, the point of these clauses is rarely to collect money. It is to make the supplier’s incentives match the buyer’s, so that the throughput and accuracy promises survive contact with a real parcel mix, a real shift pattern and a real maintenance regime. This article sets out how to draft both clauses so they hold up in operation rather than only in negotiation.

What a Performance Guarantee Actually Guarantees
A guarantee is only as good as the conditions attached to it. Every credible throughput figure is stated with qualifiers, and when they are missing the number is marketing. Six belong in the contract:
- Parcel mix and size distribution: the mix the rate was measured against, expressed in proportions rather than adjectives.
- Induction configuration: how many induction points were feeding the line, and whether they were staffed or automated.
- Measurement window: sustained over an agreed period, not the best minute of the best hour.
- Downstream conditions: chutes emptied on schedule and takeaway running, because a full chute stops a sorter regardless of its rating.
- Exclusions: what happens to no-reads, upstream starvation and recoverable jams inside the calculation.
- Accuracy definition: whether accuracy means parcels in the correct chute, correct destination, or correct after manual correction.
That list is the negotiation map. A supplier confident in the machine will state the qualifiers without argument; one who resists each of them is protecting a number that was never measured under these conditions. The parties that agree the qualifiers early usually move through acceptance in days rather than weeks.

Structuring Liquidated Damages
Liquidated damages are a pre-agreed sum payable when the machine misses a defined performance level, which removes the need to prove an actual loss later. Four design choices determine whether the clause works:
- Cap: a ceiling, usually a percentage of contract value. Buyers push for ten percent; suppliers land somewhere lower. The number matters less than the fact that it exists.
- Stepped rather than binary: a small shortfall attracts a proportional amount, a serious one attracts the full rate. All-or-nothing clauses are the ones that end in argument.
- Cure period: a defined window in which the supplier may fix the shortfall before damages accrue, plus a limit on how many times it can be used.
- Remedy position: whether damages are the sole remedy for underperformance or whether the buyer also keeps the right to reject, and the answer has to be written down.
The clause should also say what it does not cover. Availability shortfalls caused by missing site power or upstream starvation are not supplier faults.
Making the Measurement Trustworthy
Performance disputes are rarely about the machine. They are about whose numbers count. Three decisions settle it: the data comes from the sorter control system rather than the warehouse system, the reporting interval is fixed in advance, and both parties receive the raw output rather than a summary.

Technical Background
The clause itself rests on the liquidated damages mechanism, a sum fixed in the contract in place of proving actual loss. Where the supplier’s obligation is underwritten by a third party, the instrument is the performance bond, which pays out on defined default rather than on a negotiated argument. The indicators being guaranteed are the classic key performance indicators of a sortation operation: throughput, accuracy and availability, each needing its own definition before it can be measured against a threshold.
Practically, the guarantee is measured in the acceptance test described in FAT and SAT acceptance testing, and the throughput figure itself is validated by the method in how to verify CPH claims. Payment tranches are usually released against the same milestones, which is why the damages clause has to be read together with payment milestones and performance security. Across the operating life the same indicators are reported under operating data and reporting requirements, and shortfalls that show up later are handled through warranty and service response terms.
Negotiation Traps to Avoid
Three patterns cause most of the damage. The first is the average: a guarantee met on a weekly average while individual shifts fall short, which hides precisely the operational pain the buyer was buying protection against. The second is the unmeasured mix, where the guarantee references a parcel profile nobody has verified against the sorter’s actual size range. The third is the unstaffed induction, where the rate assumes more feeding points than the roster will ever support.
The counter to all three is to make the acceptance conditions the same conditions the line will actually run under. If the buyer intends to run two shifts with nine induction points and a mix that includes poly bags, the guarantee should say so, and the supplier should price that reality instead of a cleaner one. A slightly lower guaranteed number measured honestly is worth more than a higher one nobody expects to see.
Frequently Asked Questions
What is the difference between a performance guarantee and a warranty?
A guarantee states a measurable performance level and the consequence of missing it; a warranty covers the condition and repair of the equipment itself. They can overlap, and the contract should say which applies to a shortfall.
Should liquidated damages be capped?
Almost always, and the cap is normally a percentage of contract value. An uncapped clause tends to be resisted, discounted into the price, or litigated.
How should throughput be measured during acceptance?
From the sorter control system, over a defined sustained window, with the induction configuration and parcel mix stated in the clause rather than assumed.
Can damages cover availability as well as throughput?
Yes, and often they should, but availability has to exclude causes outside the supplier’s control such as missing upstream volume or site power failures.
What cure period is reasonable?
Long enough for a real fix rather than a reset, with a limit on how many times the supplier can invoke it before the shortfall is treated as accepted.
Do I lose the right to reject if I accept damages?
Only if the contract says so. The exclusivity of the remedy has to be written down, because silence on the point is what produces the dispute.
When should these clauses be negotiated?
Before the data package is finalised, while the mix and induction assumptions are still open enough to be corrected rather than defended.